Kudankulam Nuclear Power Project Units 3 and 4

India
Under Construction
Developer
NPCIL, Atomstroyexport
Capacity
2000 MWe
Last updated
10/3/2026

Project overview

Reactor type
VVER-1000
Announced
6/29/2017
Projected operational
12/31/2027

Notes

Russian-designed AES-92 VVER-1000 reactors. Construction began 29 June 2017. Physical progress 80.51 percent as of March 2026. Unit 3 expected commissioning in 2026. In April 2026, NPCIL achieved spill to open reactor stage for Unit 3. Unit 4 reactor pressure vessel lifted into position January 2025. Part of 6-unit Kudankulam complex which will be Indias largest nuclear station at 6000 MW when complete. Schedule update (September 2026): Rosatom's CEO said on September 14, 2026 that Unit 3 is in the final stages of completion, with Russia having supplied 99% of its equipment, and that its physical startup (fuel loading and first criticality) is expected in spring 2027, and that commissioning operations for Unit 4 will begin by the end of 2027; an earlier government reply in the Rajya Sabha had given 2026 for unit 3 and 2027 for unit 4. The projected operational date is moved to the end of 2027.

SMR Brief Pro members also see:

  • Risk Score: ████████
  • Opportunity Score: ████████
  • Score Rationale: ████████
  • Analyst Notes: ████████
  • Related News: ████████
  • Related Companies: ████████
  • Related Deals: ████████

Get the full intelligence dossier on every SMR project.

Track every SMR project worldwide with SMR Brief Pro

See this in the dashboard →