Fourth 700 MW PHWR in Indias fleet. Physical progress 98.60 percent as of March 2026. Hot conditioning completed. Light water commissioning in progress. Central Electricity Regulatory Commission permitted NPCIL to draw start-up power from grid till 30 June 2026 for commissioning. First synchronization expected by June 2026. The Rawatbhata site will have total 2580 MW installed capacity once Unit 8 is online.